On this project, Ruston Paving was working directly for the church. They were impressed with our professionalism and history of quality.
As sometimes it happens, while we were milling, it became evident the ground below was not suitable. We were able to approve a change order to employ a Full Depth Reclamation (FDR) process to increase stability and be able to pave the lot. We were time challenged on this one, since there would be a church service that Sunday. The managers were able to work together to make room in the schedule for the FDR.
Our lowboys enabled us to mobilize our equipment efficiently and get all necessary pieces onsite by the next morning. This allowed us to proceed with the process, which allowed us to pave Friday. Thankfully, the church was able to be open for Sunday service.